|
© Copyright 2007
Lindsay Sherwin
Click
here to access the Lindsay Sherwin Homepage and further toolkits. |
Project Control
As with project organisation, there is a danger that project
control becomes too complicated and too bureaucratic. Again the rule
should be - the simpler the better.
Certainly, major Capital and IT projects do need complex project control
procedure but they are not needed for policy and organisational projects, in
fact they tend to be more of a hindrance than help.
All project control is "control to plan" in that they all depend on comparing
actual progress to a plan (updated as the project progresses). It is helpful to
think of it operating on three levels: Strategic,Tactical, and Operational Progress. Key elements are:
Strategic
So the management of the organisation can ensure that the project is moving
at a pace that suits the organisation and its business plans, and that the
project is delivering what is required. Normally carried out by the Project
Sponsor or Project Board, in conjunction with the Project Manager.
- Initial Project Feasibility Review
The feasibility study or business
case initiating the project in the first instance.
|
To ensure that the projects undertaken are sensible and
viable. |
- Project Scoping
The Project Scoping Report presented by the Project
Manager, proposing how the project should be tackled. If a project team is
involved, involve them in the creation of the report. When it is complete, the
Project Manger should discuss and agree it with the Project
Sponsor.
|
To establish and agree the project objectives and terms of reference.
To ensure that the issues of carrying out the project are thought through and
planned right at the start. |
- End of Stage Stocktakes
A top-level plan in the form of a set of
stages with the end of each stage providing the opportunity for a stocktake and
possibly and end-of-stage report.
|
To both review project progress but also check that the original outputs and
outcomes are still valid in terms of the overall organisational
plans. |
Tactical
To ensure that the project manager has the financial and contract support to
carry out the project successfully.
- Delegations and Authorisations
At the project scoping stage agree
any delegations and authorisations needed - particularly if significant finance
is involved.
|
To ensure that people carrying out the project have the resources and powers
to resolve the difficulties they face quickly, without undue loss of
accountability and control. |
- Contract Strategy and Management
The organisational and project rules
and guidelines for contract management.
|
To ensure that any contracts are awarded fairly and based on good practice
approaches for managing contract
progress. |
Operational Progress
So that the Project Manager can keep track of project progress and know where
they need to pay attention. In this area one simply cannot avoid delving into
the detail - that is where slippage will take place.
- Project Progress Reporting - Meetings
What meetings and when
- with Sponsor and Board if applicable, with teams, with Steering/reference
groups etc. Best if linked to an end-of-stage or a key milestone, rather than
simply at regular intervals. This should form part of the Project Scoping
Report - under Project Organisation. When the Scoping Report is discussed,
Sponsor and Project Manger should agree what project reporting should be
used.
|
To keep the key people up to date on progress and to highlight any deviations
from plan.
|
- Project Progress Reporting - Written Reports
What written
reports, for whom, and when. Again, best if linked to an end-of-stage or a
key milestone, rather than simply at regular intervals. Often also based on
highlight and exception reporting.
|
To keep the key people up to date on progress and to highlight any deviations
from plan. |
- Progress Control - Project Plans and updates
The reality is that much
of operational project control in policy and organisational projects concerns
ensuring that activities will be completed on time. The key means of control for
the Project Manager in this is to:
- In Stage 3, plan the project in detail before the bulk of the implementation
starts - if it is not done now it will never be done. Use critical path analysis
or Gantt charts for this.
- As time passes, use this to check on people's progress.
- If you are using contractors, demand that they produce their own updated
plans
- When it seems necessary, re-plan the project by asking people for the "time
to complete" their particular activities.
|
To enable the project manager to remain up to date on progress and identify
and deviations from plan.
|
- Progress Control - Cost Budgets and Updates
If cost is important in
the project, do a similar exercise for them. Develop a budget, monitor it, and
get estimates of "cost-to-complete".
|
To enable the project manager to remain up to date on progress and identify
and deviations from plan. |
|