|
© Copyright 2007
Lindsay Sherwin
Click
here to access the Lindsay Sherwin Homepage and further toolkits. |
Project Stages
Stage 3 Plan, Organise and Start-Up

When the project scoping report is agreed with the sponsor, the
project is now formally "live". For some but not all projects, a Start
Up Stage is sensible. If such a stage is needed, then the Project
Scoping Report should say so.
There are two types of project where a start up stage should
be introduced.
-
Projects where the project manager needs to build/gain support
of others
- For example - a Bill or a Consensus perhaps.
- Because of the political nature
of such projects and the number of stakeholders involved, on many occasions
the project manager will need a start up stage to communicate the project,
build support, and generally prepare the ground. The project scoping report
should describe this.
-
Complex projects where there are many activities to
be organised.
- For example - many technical projects; IT systems,
spaceship, tunnel.
- Such projects need to be planned and organised in some
detail.
Typically, there are four elements:
- The Work to be done
Analysing the project and
identifying all the activities and tasks to be carried out, and then drawing-up
a time plan or schedule of them. Using this to create a map of the project.
- People
Start to plan how you will manage and
organise the people contributing to the project.
- Facilities & Materials
At the same time,
start to identify any equipment, space, or materials that may need to be
purchased or hired and identify that on the planning chart.
- Finance
Large projects, particularly capital
ones, may need cash flow planning calculations.
For most policy and organisational projects the key element
is planning the work to be done and drawing up a time schedule. This needs to
be done in some depth using planning techniques such as critical path analysis,
Gantt charts and milestone plans. Section 5 contains outlines of the key techniques.
How formal this stage needs to be and how much time it takes
depends on the particular project. For really complex projects it is best if
the Project Manager summarises the main aspects of this in a Project Implementation
Plan to be checked with contributors and agreed with the Project Sponsorship
before moving onto implementation proper.
Key Points
- There is no magic secret to planning - it is simply a
matter of investing the time to do it and being persistent in getting people
to make estimates. The latter is always difficult and often one is dealing
with sophisticated guesses.
- The main difficulty is often protecting this planning
time. The pressures for results mean that often people are "hustled"
into action before they are ready.
- If you don't do the planning at this stage it will never
get done. When events start moving, they can gain a momentum of their own
and rather than you managing the project, you become managed by it.
|