Using WORD to make a GANTT chart
There are two ways of doing this. One is to use tables and the other
is to use text boxes.
Gantt Charts using Tables
| Activities |
May |
June |
July |
Aug |
Sept |
Oct |
Nov |
Dec |
| Decide on TQM Kick-Start |
X |
|
|
|
|
|
|
|
| Steering group Chosen |
X |
X |
|
|
|
|
|
|
| Start Staff Climate Survey |
|
|
|
|
|
|
|
|
| Steering group Trained |
|
|
|
|
|
|
|
|
| Start Customer Surveys |
|
|
|
|
|
|
|
|
| Visits to other companies |
|
|
|
|
|
|
|
|
| Staff Climate Survey Complete |
|
|
|
|
|
|
|
|
| Train Other Managers |
|
|
|
|
|
|
|
|
| Complete Awareness Training |
|
|
|
|
|
|
|
|
| Facilitators Trained |
|
|
|
|
|
|
|
|
| 10 QATs formed & working |
|
|
|
|
|
|
|
|
A template for this is in
Template Word Gantt 1
- This approach uses the WORD tables. It is best to activate the
Tables and Borders toolbar by going to View, Toolbars, and clicking
Tables and orders.
- To use the template, Change the months to suit the project and
type in the activities to be carried out
- To create a table from fresh, go to insert a table in your
document and adjust as in the example below.
- For each activity, colour the appropriate cells using the Fill
tool in the Tables and Borders toolbar above.
- You can then create a simple Gantt chart similar to the one
shown below.
- Copy it and paste it into your project plan
Gantt Charts using Text Boxes
|
Gantt Chart
|
| |
|
May
|
June
|
July
|
Aug
|
Sep
|
Oct
|
Nov
|
Dec
|
Jan
|
|

|
A template for
this is in
Template Word Gantt 2.
To create the above:
- Go to
the "Table" menu, select "Insert Table", and create a table of 9
columns (the number of months needed) by 2 rows.
- The first row is the heading.
Type in the months May to Jan making each
"Bold". Then select the whole row and select grey from "Shading
Colour" in the Tables toolbar.
- Then resize the second row to the depth shown. (Cursor over the bottom
line of the second row until it changes to a resizing cursor and then drag the
line down).
- Then create the text boxes with text and colouring as described on the
previous page for STAGES. Stretch each to represent the time needed for that
activity and drag them around the chart to put them in
place.
|